Project Charter Developent
Learning Objectives
- Explain the purpose of a Six Sigma Project Charter.
- Understand the key components of a Project Charter.
- Develop a clear Problem Statement.
- Develop a meaningful Business Case.
- Define project goals using measurable terms.
- Establish appropriate project scope.
- Identify project stakeholders and roles.
- Understand project timelines and milestones.
- Establish accountability within the project team.
- Recognize and prevent scope creep.
- Understand how the Project Charter supports DMAIC execution.
- Develop a practical Project Charter for a Green Belt project.
1. Introduction
Once a suitable Six Sigma project has been selected, the next step is to formally define the project.
A Project Charter is the document that establishes the basic direction and boundaries of the Six Sigma project.
It provides a common understanding of:
- Why the project is being undertaken.
- What problem is being addressed.
- What the project is expected to achieve.
- What is included in the project.
- What is outside the project.
- Who is responsible for the project.
- Who needs to be involved.
- When the project is expected to be completed.
The Project Charter creates alignment between the Green Belt, project team, process owner, sponsor, and other important stakeholders.
A useful principle is:
A project that is not clearly defined is difficult to control.
2. Concept / Theory
2.1 What Is a Project Charter?
A Project Charter is a formal document that defines the fundamental elements of a Six Sigma improvement project.
It acts as a reference throughout the project.
The Charter does not need to contain every detail of the eventual analysis. Instead, it establishes the foundation from which the project can proceed.
A typical Project Charter includes:
- Project Title.
- Problem Statement.
- Business Case.
- Project Goal.
- Project Scope.
- Project Timeline.
- Project Team and Roles.
- Key Stakeholders.
- Preliminary Measures.
- Assumptions and Constraints, where appropriate.
The exact format may vary between organizations.
2.2 Purpose of the Project Charter
The Project Charter serves several purposes.
Direction
It provides a clear statement of what the project is intended to accomplish.
Alignment
It helps stakeholders develop a common understanding of the project.
Accountability
It establishes responsibilities for the sponsor, Green Belt, team members, and process owner.
Scope Control
It establishes boundaries and helps prevent uncontrolled expansion of the project.
Communication
It provides a concise reference that can be communicated to stakeholders.
Project Authorization
In many organizations, approval of the Charter provides formal authorization to begin the project.
3. Key Topics
3.1 Project Title
The project title should clearly communicate the subject of the improvement project.
For example:
Reducing Loan Approval Cycle Time
or
Reducing Customer Complaint Response Time
The title should be specific enough to identify the project without becoming excessively detailed.
3.2 Problem Statement
The Problem Statement describes the current performance problem.
A good Problem Statement should be:
- Clear.
- Specific.
- Fact-based.
- Measurable where possible.
- Free from assumed causes.
- Free from predetermined solutions.
A useful structure is:
What is happening + Where it is happening + When it is happening + Magnitude of the problem
For example:
The average loan approval cycle time has increased from the established historical level to 8.5 days during the current measurement period, resulting in increased customer complaints and delayed service completion.
The exact values used in an actual project should come from verified organizational data.
3.3 Avoiding a Solution in the Problem Statement
A Problem Statement should describe the problem rather than prescribe the solution.
For example:
Problem-focused:
Loan approval cycle time is longer than the required service level.
Solution-focused:
The loan approval process needs an additional approval automation system.
The second statement assumes the solution before the causes have been analyzed.
Six Sigma encourages the team to understand the problem and its causes before selecting the improvement.
3.4 Business Case
The Business Case explains why the project matters.
It connects the performance problem to organizational consequences.
A Business Case may describe:
- Customer impact.
- Financial impact.
- Operational impact.
- Quality impact.
- Strategic importance.
- Risk associated with not improving.
For example:
Excessive loan approval cycle time creates customer dissatisfaction, increases follow-up activity, and consumes additional administrative resources.
Where financial information is available, the Business Case can include estimated financial consequences.
3.5 Project Goal
The Project Goal defines what the project intends to accomplish.
A useful goal should be:
- Specific.
- Measurable.
- Relevant.
- Time-bound.
- Realistic.
For example:
Reduce loan approval cycle time by 30% from the verified baseline within the defined project period.
The target should be based on appropriate analysis and stakeholder agreement.
The Project Goal should not simply state:
Improve the process.
That statement is too vague to provide an effective measure of success.
3.6 Scope
Scope defines the boundaries of the project.
It answers:
What is included?
and
What is excluded?
Scope may be defined by:
- Process.
- Product.
- Service.
- Location.
- Department.
- Customer segment.
- Time period.
- Process stages.
For example:
In Scope:
Loan applications processed by the retail-loan department from application receipt through customer notification.
Out of Scope:
Commercial loans, mortgage products, and activities performed after customer notification.
Clear scope protects the team from unnecessary expansion.
3.7 Scope Creep
Scope creep occurs when additional activities, processes, products, locations, or objectives are gradually added to the project without appropriate review.
For example, a project initially intended to reduce retail-loan approval time may gradually expand to include:
- Mortgage processing.
- Commercial loans.
- Credit-card applications.
- Customer-service response time.
- Branch staffing.
The project can then become too large to manage effectively.
A Project Charter provides a reference point for deciding whether proposed additions are within the agreed project scope.
3.8 Project Timeline
The Charter should establish the expected project period.
A timeline may identify major milestones such as:
- Charter approval.
- Define completion.
- Measure completion.
- Analyze completion.
- Improve implementation.
- Control implementation.
- Project closure.
The exact duration depends on project complexity and organizational requirements.
3.9 Project Team and Roles
A Six Sigma project requires clearly defined responsibilities.
Typical roles may include:
Project Sponsor
Provides organizational support, removes barriers, and ensures alignment with business priorities.
Process Owner
Owns the process and is responsible for operational adoption and sustainment.
Green Belt
Leads or facilitates the improvement project and applies the appropriate Six Sigma methodology and tools.
Project Team Members
Provide process knowledge, data, technical expertise, and support for analysis and implementation.
Subject Matter Experts
Provide specialized knowledge when required.
Clear roles reduce confusion and improve accountability.
3.10 Stakeholder Identification
Stakeholders are individuals or groups who:
- Are affected by the project.
- Have influence over the process.
- Provide resources.
- Own process decisions.
- Use the process outputs.
- Are responsible for implementing or sustaining changes.
Examples include:
- Senior management.
- Process owners.
- Employees.
- Customers.
- Quality personnel.
- Finance personnel.
- Information technology personnel.
- Suppliers.
Stakeholder identification should begin early rather than after improvement solutions have already been developed.
3.11 Preliminary Project Measures
The Charter may identify preliminary performance measures.
Examples include:
- Cycle time.
- Defect rate.
- First-pass yield.
- Customer complaints.
- Cost.
- Process capability.
- On-time delivery.
- Response time.
The detailed operational definition and measurement-system assessment can be developed during the Measure phase.
3.12 Assumptions and Constraints
Projects may operate under assumptions and constraints.
Examples include:
Assumptions
- Required process data will be available.
- Key personnel will participate.
- The process will remain sufficiently stable during the study period.
Constraints
- Limited project resources.
- Regulatory requirements.
- Technology limitations.
- Fixed project deadlines.
- Limited access to certain data.
Documenting important assumptions and constraints improves project transparency.
4. Tools / Methodology
4.1 Project Charter Development Process
A practical Charter-development process can follow these steps.
Step 1 — Confirm the selected project
Verify that the project addresses the previously identified business or customer problem.
Step 2 — Develop the Problem Statement
Describe the current performance problem using factual information.
Step 3 — Develop the Business Case
Explain why solving the problem matters.
Step 4 — Establish the Project Goal
Define the desired measurable improvement.
Step 5 — Define the Scope
Specify what is included and excluded.
Step 6 — Identify Stakeholders
Identify people who influence, support, perform, receive, or are affected by the process.
Step 7 — Establish Roles
Assign appropriate responsibilities to the Sponsor, Green Belt, Process Owner, and team members.
Step 8 — Establish the Timeline
Define major project milestones.
Step 9 — Identify Preliminary Measures
Identify the key performance indicators that will be used to understand the problem.
Step 10 — Review and Approve the Charter
Review the Charter with relevant stakeholders and obtain appropriate approval.
4.2 Project Charter Template
A Green Belt Project Charter can be structured as follows:
| Charter Element | Description |
|---|---|
| Project Title | Concise name of the project |
| Problem Statement | Current measurable performance problem |
| Business Case | Why the problem matters |
| Project Goal | Desired measurable improvement |
| Scope | Boundaries of the project |
| Out of Scope | Explicit exclusions |
| Sponsor | Executive/project sponsor |
| Process Owner | Owner of the affected process |
| Green Belt | Project leader/facilitator |
| Team Members | Supporting project members |
| Stakeholders | Important affected or influencing parties |
| Timeline | Project period and milestones |
| Preliminary Measures | Key performance indicators |
| Assumptions | Important conditions assumed |
| Constraints | Important limitations |
The organization can adapt this template to its own governance requirements.
5. Worked Example / Case Study
Case Study — Reducing Late Deliveries by 30%
A logistics organization has identified a recurring problem with late customer deliveries.
Management has selected the issue as a potential Green Belt project because:
- Customer complaints have increased.
- Delivery performance has deteriorated.
- The problem is measurable.
- Delivery records are available.
- The process has an identifiable owner.
- The problem has business significance.
Project Title
Reducing Late Customer Deliveries
Problem Statement
A review of recent delivery-performance data indicates that the percentage of customer orders delivered after the promised date is above the organization’s required performance level.
Business Case
Late deliveries can result in:
- Customer dissatisfaction.
- Additional customer-service contacts.
- Expediting costs.
- Additional administrative effort.
- Potential loss of customer confidence.
Improving delivery performance can therefore provide customer and operational benefits.
Project Goal
Reduce the percentage of late customer deliveries by 30% from the verified baseline within the agreed project period.
Scope
In Scope:
The order-fulfillment process from confirmed customer order through delivery for the defined distribution operation.
Out of Scope:
Activities outside the agreed distribution operation and product categories not included in the project.
Project Team
Sponsor: Senior operations manager
Process Owner: Logistics manager
Green Belt: Assigned improvement practitioner
Team Members: Representatives from order processing, warehouse operations, transportation, and customer service.
Preliminary Measures
The project may initially consider:
- On-time delivery percentage.
- Delivery cycle time.
- Number of late deliveries.
- Customer complaints related to delivery.
The final operational definitions will be established during the Measure phase.
Timeline
The project timeline can include:
Charter Approval → Define → Measure → Analyze → Improve → Control → Closure
The specific dates should be established according to organizational requirements.
Result
The Charter establishes a common understanding of the project before detailed data analysis begins.
It provides the Green Belt and stakeholders with a clear reference for project direction, scope, responsibilities, and expected results.
6. Practical Application
Exercise — Develop a Project Charter
Consider the following situation:
A customer-service department has experienced an increase in response time for customer email requests.
Customers expect responses within the organization’s defined service standard.
The department has historical response-time records and receives regular customer complaints related to delayed responses.
Develop the major elements of a Project Charter.
6.1 Project Title
Create a concise title describing the improvement opportunity.
6.2 Problem Statement
Describe:
- What is happening?
- Where is it happening?
- When is it happening?
- What evidence demonstrates the problem?
Avoid identifying the cause before analysis.
6.3 Business Case
Consider:
- Customer impact.
- Operational impact.
- Financial implications.
- Strategic importance.
6.4 Project Goal
Develop a measurable improvement goal.
The goal should include an appropriate performance measure, baseline or reference point, improvement target, and timeframe where these are available.
6.5 Scope
Define:
In Scope
and
Out of Scope
This prevents the project from gradually expanding into unrelated customer-service issues.
6.6 Stakeholders
Identify:
- Sponsor.
- Process Owner.
- Green Belt.
- Team Members.
- Customer-service representatives.
- Customers or customer representatives where appropriate.
- Supporting functions.
6.7 Preliminary Measures
Potential measures might include:
- Average response time.
- Median response time.
- Percentage of responses meeting the service standard.
- Number of customer complaints.
The Green Belt should avoid assuming which measure is most appropriate before understanding the process and data.
7. Lesson Summary
The Project Charter establishes the foundation for a Six Sigma project.
A well-developed Charter should clearly communicate:
- The problem.
- The business reason.
- The project goal.
- The project scope.
- The stakeholders.
- The roles and responsibilities.
- The timeline.
- The preliminary performance measures.
- Important assumptions and constraints.
The Problem Statement should describe the problem rather than prescribe a solution.
The Business Case explains why the problem matters.
The Project Goal establishes the intended measurable improvement.
The Scope defines project boundaries and helps prevent scope creep.
Clear roles and stakeholder identification establish accountability and improve alignment.
The Charter should be reviewed with appropriate stakeholders before the project proceeds into detailed DMAIC execution.
8. Lesson Learnt / Conclusion
A Project Charter converts an improvement opportunity into a clearly defined project.
It creates focus, accountability, stakeholder alignment, and protection against scope creep.
A strong Charter does not attempt to solve the problem before the team has investigated it. Instead, it establishes the conditions under which the problem will be studied and improved systematically.
Green Belt Takeaway:
A clear Project Charter creates focus, accountability, and alignment before the improvement work begins.